February 3, 2009
INDIANA BULLETIN NO. IN 300-9-3
SUBJECT: LTP - Program Contracting System (PROTRACTS) Evaluations
Purpose:
To provide additional guidance on conducting Contract Reviews
Expiration Date:
September 30, 2009
Contract evaluation is the “follow-up” part of the conservation planning
process. DCs will review contract implementation annually,
adhering to policy set forth in 440 CPM, Part 512.55 (Contract Reviews).
AC’s will notify the State Conservationist by September 1, 2009, that
all field offices have completed the review of their ProTracts contracts
utilizing the “Contract Review Module” in Protracts for FY 2009,
including completing all activities described below associated with
contract reviews.
If all contract provisions are being
followed and implementation is on schedule:
-
Document contract status in the contract review module in ProTracts
by checking YES to the question “All other contract provisions
met?” No further action is necessary.
If the practice application is not
on schedule or provisions of the contract are not being followed:
- The
NRCS District Conservationist will review with the participant and
document the specific cause of the potential contract violation
findings in ProTracts on Form NRCS-CPA-13 (sample attached),
citing the contractual basis for the potential violation ( 512.70 of
the CPC). When contract items cannot be completed in the year
scheduled but will be completed not later than one year after the
originally planned year, a contract modification in Protracts will
not be required to delay the practice. This provision shall be
noted on a formal contract review using form NRCS-CPA-13.
- The
contract review completed in ProTracts on NRCS-CPA-13, will be
signed by the NRCS District Conservationist completing the review.
A copy will be provided to the participant, and the original will be
placed in the contract folder. DC’s will elevate “non-typical”
situations to their respective Area Conservationist.
- The
DC will work with the participant(s) to resolve all issues and
document all actions that need to be taken to complete the contract,
including establishing a reasonable timeframe for the participant to
comply with the contract provisions. Repeat modifications to
reschedule practices are not allowed. The DC will also provide to
the participant, a notification of the consequences of failure by
the participant to remedy the potential contract violation.
The attached “Corrective Action Plan Covering Non-Compliance with
Provisions of Contract” shall be used for this purpose in lieu of
the NRCS-CPA-153, and it shall be signed by the District
Conservationist, and the participant. A copy will be provided to
the participant, and the original will be placed in the contract
folder.
- If
the participant cannot or will not complete the contract obligations
as previously agreed to in the “Corrective Action Plan Covering
Non-Compliance with Provisions of Contract”, follow the procedures
established in CPC (512.57) and Indiana policy (IN Bulletin 300-9-2)
to terminate the contract. The participant may voluntarily request
cancellation in writing using the process set up in Indiana Bulletin
300-9-2.
For more
information contact Teresah P. Caire, Assistant State Conservationist
for Programs, at 317-290-3200, ext. 3.
/s/
Gary L. Maners {Acting For}
JANE E.
HARDISTY
State Conservationist
Attachments:
Contract Review NRCS-CPA-13
Indiana Corrective Action Plan
|
|